The Masjid construction has been divided into the following phases:                   Please Help Us Complete This Center 

PHASE 1 Scope: Land Purchase, Architecture Design, Foundation, Parking lot, Prayer Hall, Wudu Area, Bathrooms

  • Phase 1A - Land Purchase - Complete
  • Phase 1B - Architecture Design, Survey, & Pre-Engineering -Complete
  • Phase 1C - Site Development Work & Permanent Parking Lot - Complete
  • Phase 1D - Laying the Foundation and Building Structure - Complete
  • Phase 1E - 1st floor Interior Finish and Occupancy permit from the City - Complete

PHASE 2 Scope: 2nd Floor, Classrooms, Offices, Kitchen, Rooftop Dome and Minarets

*** Contract Signed with Construction Company on May 20th. Work to Be Completed in Less than 180 Days*** 

  • Phase 2A - 2nd floor Architecture Design & Survey- Complete
  • Phase 2B - 2nd floor Interior Finish and Occupancy permit from the City- In Progress
  • Phase 2C Rooftop Dome and Minarets

PHASE 1  Complete           BUDGET- $3.1 MILLION

Grand Opening  10/21/14

 

PHASE 2 BUDGET: $890,000

RAISED: $250,000   *as of 05/15/16

PHASE 2B           *** Contract Signed with Construction on May 20th. Work to Be Completed in Less than 160 Days*** 

  • Scope: 2st Floor interior Finish including Classrooms, Lecture Hall, Kitchen, and Offices. And City occupancy permit,
  • Budget: $420,000

PHASE 2C-TBD

  • Scope: Rooftop Dome and Minarets
  • Budget: $200,000

 

 

Prayer Schedule

ADHAN IQAMAH
FAJIR
DUHR
ASR
MAGHRIB
ISHA

JUMMA (FRIDAY) PRAYERS

1st Khutbah 12:30 pm
2nd Khutbah 1:30 pm

Make a Donation

Please help us build the Masjid so that Allah may build a house for you in Jannah.


Goal: $450,000 Last Updated on 11/28/2016